As if the first week of the new school year for Nevada’s higher education students isn’t busy enough, it’s also the second week of Phase 3 unit testing. Many Testing Team members are pulling double duty, working at their jobs on campuses that have blown up with increased non-Project activity, and also spending hours putting NSHE’s Workday configuration through its paces. Thanks to ceaseless efforts put forth by all the Testers, over 65% of Phase 3’s nearly 1,200 scenarios have been completed. The failed scenario rate fell this week to 2% from last week’s 5%, showing that NSHE’s Workday configuration is well aligned with its planned business processes. Phase 3 unit testing is scheduled to be completed on September 9th. Way to go, Testers!
Progress Stats as of 12:10pm Friday, 9/2/16
- Number of Testers: 60
- Total Scenarios to Test: nearly 1,200
- Scenarios Completed: 67%
- Scenarios Completed and Passed: 59%
- Scenarios Completed and Failed: 2%